Methane Camera inspections

Measuring and controlling methane emissions is a major problem for all industries. National and international treaties require a rapid reduction of greenhouse gas emissions. In addition to the associated health and safety risks at industrial sites, methane emissions result in lower profitability for the industry, therefore there is an increasing need to detect, monitor and…

Biogas and heating plant at the sewage treatment plant in Zaandam

Commissioned by Solvoy b.v., Biogas Holland has been contracted to design, manufacture and install a biogas and heating plant at the sewage treatment plant in Zaandam. With this installation,  Hoogheemraadschap Hollands Noorderkwartier (HHNK) has the possibility to purify their biogas and convert it into electricity and heat by means of CHP and heating boilers. With…

Biogas treatment at the sewage treatment installation of Willem Annapolder

Commissioned by ELIQUO Water & Energy BV, Biogas Holland B.V. has been contracted to realize a biogas treatment for Waterschap Scheldestromen at the sewage water treatment plant of Willem Annapolder. The biogas treatment follows a biogas scrubber developed in-house by Eliquo and Waterschap Scheldestromen, which largely removes hydrogen sulphide (H2S), so that the addition of…

Flexible and mobile, Verdygo biogas plants at RWZI Weert

Sewage treatment plants in the Netherlands face the challenge of having to anticipate varying amounts of wastewater with different types and degrees of pollution. In collaboration with Mobilis, Croonwolter&dros and Eliquo, Biogas Holland has been able to realize a biogas treatment for WBL that works in a biogas production of 75 to 450 m³ / hour…

Optimal energy generation from sewage water at RWZI Limmel

Commissioned by ELIQUO Water & Energy BV for Waterschapsbedrijf Limburg, we have been able to realize a sustainable energy generation at the Limmel sewage water purification plant in Maastricht! The Verdygo Biogas Treatment ensures that the “dirty” biogas is cleaned from hydrogen sulphide, siloxanes and water. The subsequently realized CHP (Combined Heat and Power) converts…

Adjustment and expansion of AWZI Tollebeek

Waterschap Zuiderzeeland has recently expanded its sludge digestion line. In addition, the conventional fermentation technology is supplemented with an Ephyra installation, resulting in a higher fermentation yield. From now on, not only their own sludge, but also the sludge from the Lelystad WWTP will be processed into biogas. This biogas is burned in a high-efficiency…

Renovation of biogas plant WWTP Den Bosch

Biogas Holland has provided the engineering, delivery, installation and commissioning of a new gas holder and condensate drain at the WWTP Den Bosch of Waterschap Aa en Maas, commissioned by the Besix-Hegeman in combination with the biogas treatment commissioned by Colsen. This innovative project focuses on minimal energy consumption and maximum yield of biogas. Expansion…

RWZI Zwolle, energy neutral and supplier to 1500 households

Biogas Holland has replaced the gas holder, CHP (Combined Heating and Power), gas treatment and gas flare at RWZI Zwolle of Waterschap Drents Overijsselse Delta on behalf of ADS Groep. As a result of the work that has been carried out, RWZI Zwolle has become independent in energy consumption and becomes an energy producer. Energy…

Clean biogas for RWZI Franeker

The complete biogas utilization has been renewed at the RWZI  Franeker. To provide the new biogas boiler and CHP with the correct quality gas, Biogas Holland has built a biogas treatment installation on behalf of Eliquo Water & Energy BV at the location of Wetterskip Fryslân in Franeker.   Treat and utilize Biogas is produced at RZWI…